We’re carrying out preventative maintenance on roads across Central Bedfordshire to help protect them from deterioration and keep them in good condition for longer.

During November 2026, our highways teams will be using micro asphalt on selected roads as part of our wider work to keep Central Bedfordshire moving.

Rather than waiting for roads to deteriorate and require more extensive repairs, micro asphalt allows us to step in earlier. The treatment helps protect the road surface from water and winter weather, extends its lifespan and reduces the need for more disruptive work in the future.

What is micro asphalt?

Micro asphalt is a thin, protective layer applied over the existing road surface.

It is generally used on roads that are still structurally sound but are beginning to show signs of wear. The treatment seals the surface, helping to prevent water getting into the road structure and causing further deterioration.

It can also address minor surface defects and improve the texture and skid resistance of the road.

By carrying out this work at the right time, we can help extend the life of the road by up to 10 years, reducing the need for more costly repairs later and helping us make the best use of the money available to maintain roads across Central Bedfordshire.

What are the benefits?

Micro asphalt:

  • helps protect roads from water and weather damage
  • can extend the life of a road surface by up to 10 years
  • improves the condition and texture of the carriageway
  • can improve skid resistance
  • reduces the likelihood of more extensive repairs being needed later
  • can be completed more quickly and with less disruption than full resurfacing

What should residents expect?

Micro asphalt can look different immediately after it has been laid. The surface may initially appear brown but will gradually turn black as the material settles and cures.

There may also be some loose chippings immediately after the work. Traffic helps bed these into the new surface and our highways teams will return to sweep away any excess material.

The treatment typically adds around 15mm to 20mm to the road surface, which means manhole covers, drains and other ironwork may temporarily sit below the new surface.

Within 4 weeks after the initial treatment, our teams will return to:

  • adjust manhole covers, drains and other ironwork to the correct level
  • remove any remaining loose material
  • replace road markings where required

This follow-up work is a normal part of the process and completes the treatment.

Why can the dates change?

Micro asphalt can be applied in cooler weather but requires dry conditions, so works may be postponed if it rains. Temporary road closures will be needed during the works to keep road users and the workforce safe, with access maintained wherever possible. Residents will receive advance notice through letter drops and warning signs.

How can residents help?

If micro asphalt works are taking place on your road, please:

  • do not park on a neighbouring road where possible to allow the works to take place, follow signage on site
  • make sure vehicles are parked in accordance with the Highway Code
  • avoid sudden braking or steering manoeuvres on the newly treated surface until it has fully dried
  • take extra care at junctions until give way and centre line markings have been replaced

2026 micro asphalt programme

The current programme has these expected start dates:

  • Park Hill, Toddington – 4 November
  • Saturn Close, Leighton Buzzard – 3 November
  • Service Roads, Leighton Buzzard – 2 November
  • St Michaels Avenue / Watling Place & Roman Gardens, Houghton Regis – 30 October
  • Mill Lane, Langford – 5 November
  • Newlands Road, Westoning – 5 November
  • Hornbeam Close, Leighton Buzzard – 3 November
  • Wallace Drive, Eaton Bray – 30 October
  • Columba Drive, Leighton Buzzard – 3 November
  • Eddiwick Avenue, Houghton Regis – 1 November
  • Gemini Close, Leighton Buzzard – 1 November
  • Drury Lane, Houghton Regis – date to be confirmed in March 2027

Dates are subject to suitable weather and site conditions and may change at short notice.

For information about works taking place on a particular road, please follow the advance signage and local communications provided.