Gateway 1 Self Assessment – Local Plan 2050

The Town and Country Planning (Local Planning) (England) Regulations 2026 require us to undertake a self-assessment of readiness to start the 30 month process for preparing a Local Plan, known as Gateway 1. This self-assessment explains what we did to get ready to meet the 30 month timeframe, includes links to further information and explains where to get updates on the preparation of the Local Plan.

The Central Bedfordshire Local Plan 2050 will set out a strategy for future growth by allocating sites to meet our future development needs, and includes policies covering local issues that will be used to assess development proposals and protect our important local assets.

Work on the Local Plan started in January 2024 with early engagement, preparing evidence studies and undertaking the call for sites. The government subsequently introduced a new plan making system in March 2026 with the publication of the Town and Country Planning (Local Planning) (England) Regulations 2026. All work undertaken prior to this is being used to inform the content of the new Local Plan.

Publishing a timetable for preparing the Local Plan

We published our Notice of Intention to Commence Plan Making and Local Plan Timetable on 26 March 2026. The timetable sets out the main stages of plan making through to adoption and gives residents and other stakeholders a clear understanding of when we expect to carry out the different stages and when they can get involved. 

The timetable is being reviewed monthly, and any amendments to the timing of different stages have been explained on the webpage.

The timetable shows that we intend to adopt the Local Plan by December 2028, meaning that the plan will be prepared, examined and adopted within the prescribed 30 month timeframe.

However, there are several issues outside of our control that the Local Plan will need to respond to, including the Universal Studios scheme, East West Rail and the government’s New Towns Programme. This may have an impact on the timetable moving forwards. The timetable will be kept under review, and any updates will be clearly set out on the webpage as the plan progresses.

Establishing project management and governance arrangements

Preparing a Local Plan is a complex process that involves many of our people and those from other organisations. Having project management and governance in place helps us to monitor how the work is planned, managed and signed off and keeps the work on track. It also helps us anticipate and manage any risks to adopting the Local Plan within the 30 month programme.

We have an established programme management system in place that includes the risks, resources and key milestones for delivering the Local Plan. This has been in place since work on the Local Plan commenced in 2024 and it is reviewed regularly. We also have a detailed project plan and dedicated programme manager in place to manage all the individual work areas, to ensure that the key stages of the plan can be met in accordance with the timetable.

With regards to governance, there is a Local Plan Project Board in place that brings together lead officers from all our service areas. The board meets quarterly (or more frequently if needed) and is a forum to share key information about the Local Plan. It also acts as a sounding board for approaches and decisions. Topic specific working groups are also being set up to help develop the content of the Local Plan, and these may also include external stakeholders including infrastructure providers. 
Regular meetings are held with the Portfolio Holder responsible for the Local Plan and all Member briefings are also held at key stages.

Our Constitution provides the legal and procedural framework for how we operate, make decisions, and ensures transparency and accountability. In accordance with the Constitution, the Local Plan forms part of our policy framework and as such key decisions on the Local Plan are a Full Council function, following an Executive recommendation. This includes commencement of the Local Plan, agreement to consult at formal stages of plan making, submission and adoption.

The project governance arrangements will be set out in our Engagement and Governance Strategy.

How we will consult on the Local Plan

We are preparing an Engagement and Governance Strategy to support the preparation of the Local Plan. This strategy reflects the approaches previously set out in the Statement of Community Involvement (SCI) as well as the feedback received through the Scoping Consultation, and an early Engagement Study that we prepared at the outset of the plan making process.

The Engagement and Governance Strategy will set out how residents, businesses, local organisations, statutory consultees, under-represented groups and other stakeholders will be engaged throughout the preparation of the Local Plan. It will set out what we will do as a minimum at each stage of plan making. We will reflect on each stage of engagement and consultation to identify what worked well and what did not; and may adapt and tailor our approach at each subsequent stage to ensure our engagement methods are effective and proportionate.

We have established consultation and engagement processes that we’ll be using to facilitate participation during plan making. This includes widespread communications (press releases, social media and emails), online surveys, website updates, printed materials in our offices and in libraries across Central Bedfordshire and targeted engagement with underrepresented groups.

All feedback received will be recorded, analysed and reported to demonstrate how it has been taken into account in subsequent stages of plan preparation.

Scoping the content of the Local Plan

To identify the scope of our Local Plan, we have looked at existing evidence about our area and the people our plan needs to provide for. We have also considered our adopted Local Plan and what might need changing, and how we can deliver our aspirations in line with our Strategic Plan, Sustainability Plan and Vision 2050. We have also used the valuable feedback we received through our scoping consultation and early engagement.

Using the information we have gathered, we have:

  • drafted a vision for the area
  • developed an understanding of the needs of the area and identified our key priorities and the objectives for delivering them
  • identified a high level, preferred strategy for delivering new homes and jobs
  • looked at what new local planning policies we need for decision making about new developments, taking into consideration the policies in new National Planning Policy Framework

Strategic Environmental Assessment

We are legally required to identify, describe and evaluate the likely significant effects of the Local Plan on the environment. This is done through a Strategic Environmental Assessment (SEA) which considers the effects of implementing the Local Plan and any reasonable alternatives at all key stages.

The SEA process considers how community, national and international environmental protection objectives and any other environmental challenges are taken into account in the Local Plan. It will help us to predict any significant environmental effects and develop ways of preventing, reducing and offsetting these.

A SEA Scoping Report has been prepared to identify relevant plans and programmes and set out baseline information looking at Central Bedfordshire’s environment and relevant designations to identify potential issues and problems. The SEA Scoping Report was published in July 2026, and we consulted the Environment Agency, Natural England and Historic England in accordance with legal requirements. We also held a public consultation to allow residents and stakeholders to share their views. The SEA Framework has been informed by the responses we received.

A SEA has been prepared alongside the Regulation 23 consultation document to appraise the strategy options and will be published as part of the consultation on 30 November 2026.

SEA Scoping Report (consultation version)

Conclusion

The Gateway 1 Self Assessment demonstrates that we have established programme management, engagement and governance arrangements for the Local Plan, and have also met the legislative requirements to proceed to the Regulation 23 stage.

The Local Plan will proceed with consultation on the Regulation 23 plan on 30 November 2026, subject to Full Council approval.

How to stay up to date

Sign up for email alerts to be kept informed about upcoming consultations on the Local Plan.