In January, 2024, our Development Management Committee approved the plans for a new leisure centre in Leighton-Linslade.
Construction on the site in Clipstone Brook, served by Briggington Way, east of Leighton Buzzard started on site in October 2024.
Project timeline
April – July 2022
Consultation on the plans for a new leisure centre.
View the Statement of Community Engagement (PDF)
11 October 2022
Executive Committee decision to proceed.
November 2022
Planning application submitted
January 2024
Planning application approved.
June 2024
Construction partner appointed.
October 2024
Commencement of work on site.
27 June 2026
Leighton Leisure and Community Centre to open.