Spring 2017

Woodside Link and A5-M1 Link due to open to public.

January 2016 to May 2016

Reconstruction of Porz Ave / Poynters Rd / Park Road North roundabout.

December 2015 to May 2016

Installing street lighting, safety fencing, environmental barriers, road signs, traffic signals and establishing footpaths.

November 2015 to April 2016

Surfacing.

October 2015 to January 2016

Installing Sandringham Drive retaining wall.

August 2015 to January 2016

Key structures to be constructed:

  • Houghton Brook Bridge
  • Parkside Bridge
  • Houghton Box Culvert (August 2015 to October 2015)

July 2015 to March 2016

Drainage work.

June 2015 to January 2016

Roundabout construction at Sundon Road.

May 2015

Construction work began - majority of earthworks to be completed by October 2015.

November 2014 to January 2015

Replacing and rerouting underground some of electricity cables in 'wedge' between Sandringham Drive and Wheatfield Road.

September 2014

Development Consent Order granted.

October 2013 to April 2014

Planning Inspectorate’s Examination in Public - A timetable of this stage can be found on the Planning Inspectorate website (link opens in new window). You can also find out more about Examinations in Public on the Planning Inspectorate website. (link opens in new window)

May 2013

Development Consent Order application to Planning Inspectorate.

November 2012

Central Bedfordshire Council’s second consultation.

October 2012

Central Bedfordshire Council Executive gives approval to Woodside Link.

January 2009

Central Bedfordshire Council’s first consultation.